holidays and days off not saving on the calendar

R

Ressie

Hi,
I usually open my resource pool along with my project file. When I change
working time to refect holidays and other days off on the calendar, these
setting don't save when I re-open my project file. Is there something I'm
doing wrong? Pls. help.

Ressie
 
J

Jan De Messemaeker

Hi,

The problem may be that you say "the calendar" as if there were only one.
The resoruce has a calendar in the pool and one in the sharer file.
When you connect the file to the pool you have to decide which one will be
used in scheduling by the option "Pool takes precdence/Sharer takes
precendence).
That may explain the difference.

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 