How can we show the task's total manpower as a coloumn?

M

mike

I want to show the total planned manpower in the "gantt view" as a single
coloumn regardless of the resource name and the resource time.
 
J

JulieS

Hello Mike,

Try adding the work column to the table. Insert > Column and in the
column definition dialog box, find the field named work. You may add a
title by entering text in the title area but if you leave it blank it
will just show the name of the field.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 