D
darci
in my project plan, I need a task to occur 7 days prior to another task - it
is not dependent upon something being completed, but dependent on the
potential day something in the future will be completed. ie a dress
rehearsal 1 week before an actual go live. the go live date is dependent
upon many other tasks, but the dress rehearsal is dependent more on the date
of the go-live rather than any of the predecessor tasks of the go
live....make sense? Anyway - is there a way to create a future dependency
without setting a specific date for the task - we are still working with the
plan and do not want to put a solid date in for any tasks?
is not dependent upon something being completed, but dependent on the
potential day something in the future will be completed. ie a dress
rehearsal 1 week before an actual go live. the go live date is dependent
upon many other tasks, but the dress rehearsal is dependent more on the date
of the go-live rather than any of the predecessor tasks of the go
live....make sense? Anyway - is there a way to create a future dependency
without setting a specific date for the task - we are still working with the
plan and do not want to put a solid date in for any tasks?