how do I calculate total of subtasks into summary task duration?

S

SV

I am putting in duration in hours and divided the tasks into subtasks and
summary tasks. but the summary task is not showing the total of the subtasks
duration. how do I add the duration of all the subtasks and fill up the same
in duration field for the summary task?
 
M

Mike Glen

Hi SV,

Welcome to this Microsoft Project newsgroup :)

You can't! Duration, by definition, is the working time between the task
start time and its finish time. The Duration of a Summary is thus the
working time between the first task and the last task, and can only equal
the sum of the sub-tasks if their precedences are linked in a single chain.
You cannot therefore enter a Duration of a Summary task as this will always
be calculated for you by Project.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 