How do I change the Default start Date in MS Project 2003?

H

Hamid

Currently thedefault start date is set to 2/23/05. I need it to be the start
date for the first task. How Do I change the default start date?
 
H

Haris Rashid

Hi Hamid,

On the menu bar click Project and then click Project Information. In the
Dialog box change the Project Start Date.

Kind regards,
 