How do I 'hide' completed tasks, to remove clutter?

I

IanB

I have a large project with 150 tasks - half of which are complete. I would
like to suppress these so that viewing the project only shows
outstanding/incomplete tasks.
 
B

Brian Kennemer

IanB said:
I have a large project with 150 tasks - half of which are complete. I
would like to suppress these so that viewing the project only shows
outstanding/incomplete tasks.

this could be done with a view that used a filter that showed only
tasks with an Actual Finish date or tasks where Percent Complete was
100.
 
I

IanB

Many thanks Brian!

Brian Kennemer said:
IanB said:
I have a large project with 150 tasks - half of which are complete. I
would like to suppress these so that viewing the project only shows
outstanding/incomplete tasks.

this could be done with a view that used a filter that showed only
tasks with an Actual Finish date or tasks where Percent Complete was
100.

--

Brian Kennemer
microsoft consulting services
brian[period]kennemer[the "at" symbol]microsoft[period]com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top