First, remember that duration is the difference between the start and end
dates MINUS any non-working time in that interval. So a task that starts on
Wed and ends the following Tue has 5 days duration, not 7, because Sat and
Sun are non-working days. Also, duration is always calculated in hours and
converted to and from days for display by the conversion factor in the
"Hours per Day" setting on the calendar options page. If that setting is
the standard 8 hours per day, for a part-timer whose calendar shows a 4-hour
workday 1 "day" of duration will require them to work 2 shifts, 2 of their
workdays. If you take a task that is 10 days duration (12 or 14 days of
elapsed time depending on whether the start date puts the total run of the
task to extend over 1 weekend or 2) and assign it to a part-timer whose
calendar shows they work 8am-12noon, the duration will remain at "10 days"
but the elapsed time shown by the Gantt chart bar and the difference between
the start and end dates will encompass 4 5-day work weeks.
Create a simple project with 1 task and 2 resources. Adust the calendar for
the second resource to show 8am-12noon as their hours of work. Split the
screen and use the bottom window to assign your resources and and adjust
your percentages and you can see exactly what is happening with each case
you ran in your experiment. Remember that your part-time resource must show
up for work TWICE, working 2 successive scheduled workdays, in order to work
for 1 8-hour "day" of duration as shown in the duration column and @ 75%
assignment the 8 hours of working time results in 6, not 8, man-hours of
work being accomplished. For you part-timer to do 30 hours of work, working
75% of a 4 hour workday, they need to come to work 10 times. Each 2 times
coming to work is counted as 1 "day" of duration because they have to come
to work twice for 8 hours of duration to pass. So the elapsed time drawn by
the Gantt chart bar will cover 2 work weeks but the duration column will
read "5 days"
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I tried it multiple different ways, and here are the results:
1) Add Resource 1 @ 75%, and then add Resource 2 @ 75%. Duration
calculates at 9.83d. The difference between the Start and End Dates is
13d.
2) Add Resource 1 and Resource 2 @ 100%, then change Resource 1 % to 75%,
and then change Resource 2 % to 75%. Duration calculates at 10d. The
difference between the Start and End Dates is 14d.