K
Knutschfussl
My team of 6 people has to complete 90 tasks in 5 working days. The
allocation of the task should be so that each resource takes about 40 hours
to complete all tasks. It does not matter to the project in what order each
of them complete their tasks. It also does not matter if they are not doing
any tasks on any particular day, all tasks need to be finished at the end of
the 5th day.
How can I realise this in project. If I put in a duration of a day or less
project signals that all tasks need to be done on the first day and obviously
the resources are then displayed as overworked. If I put in that each task
only takes x% of a resources time and I then put into project when it was
actually started and actually finished Project doesn't accept the actual work
done on the task, and when I enter the actual work done on the task, it
changes the duration again.
So how can I find a better resolution for this in Project?
thanks a million!
allocation of the task should be so that each resource takes about 40 hours
to complete all tasks. It does not matter to the project in what order each
of them complete their tasks. It also does not matter if they are not doing
any tasks on any particular day, all tasks need to be finished at the end of
the 5th day.
How can I realise this in project. If I put in a duration of a day or less
project signals that all tasks need to be done on the first day and obviously
the resources are then displayed as overworked. If I put in that each task
only takes x% of a resources time and I then put into project when it was
actually started and actually finished Project doesn't accept the actual work
done on the task, and when I enter the actual work done on the task, it
changes the duration again.
So how can I find a better resolution for this in Project?
thanks a million!