I want to be reminded to perform a task (call a subcontractor) in advance of
that persons' task starting. The time in advance would be different for each
of the contractors as their availability could vary and not all tasks need
the reminder. Therefore I can not use a custom field with a formula as, at
least as far as I can tell, it would use the same lead time and apply to all
tasks. I'm using Project 2003 Enterprise with Office 2003 and WinXP.
Thanks in advance
that persons' task starting. The time in advance would be different for each
of the contractors as their availability could vary and not all tasks need
the reminder. Therefore I can not use a custom field with a formula as, at
least as far as I can tell, it would use the same lead time and apply to all
tasks. I'm using Project 2003 Enterprise with Office 2003 and WinXP.
Thanks in advance