How do I set up a task during all the project?

P

Paulo Calvário

I would like to have a task "Coordination" along with all the project, that
means, that starts on the kick-off meeting and ends with the last task of the
project. I pretend also that the duration of the task changes if those dates
changes.
It seams that it should be "Start-to-start" with the kick-off meeting and
finish-to-finish with the last task.
The problem is that in this way the duration does not change and remains
only one day.

Can you help me?

Regards
Paulo
 
P

Paulo Calvário

Hi Julie,

You was faster than my shadow!!!
It was exactly what I was looking for.

Thank you very much
Paulo

"JulieS" escreveu:
 
J

JulieS

Hi Paulo,

Glad to have helped and thanks for the feedback! Please let us know if we
can help again.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top