DerekM
never happen as planned or happen out of order from my plan.
I have a software schedule that has many books for our documentation dept,
in the beginning I entered all the tasks for all the books with resources and
could easily see the end date of any resources. Now as the project has moved
along I've found that resources move to different tasks out of order and
complete tasks as % every week. Its becoming a nightmare to see how much
work is left/end date for each resource because the predecessors are not
lined up anymore.
HELP!!!!