Hi
I have a global calendar published in Project Server (in the global model)
and a project using it.
I have changed the global calendar adding some holidays, saved and published
it but it haven't changed the calendar in the project that is using it.
How can I make the changes in the global calendar be reflected in the
projects that use that calendar as a base calendar?
Thanks
Marcos
I have a global calendar published in Project Server (in the global model)
and a project using it.
I have changed the global calendar adding some holidays, saved and published
it but it haven't changed the calendar in the project that is using it.
How can I make the changes in the global calendar be reflected in the
projects that use that calendar as a base calendar?