How to push the activities to late start

J

John

I want to know how I can push all activities fron early start to lat start
and have a new bar chart.
I also want to know how I can generate a S-curve from a cost loaded bar chart.
 
J

Jim Aksel

1. Change all activities to "As Late As Possible"
2. Use the "Analyze time scaled data in Excel" wizard available from the
tools menu.

You need to specify the PV, EV, AC fields in your output.
Before you do so, set the "Status Date" (Project/Project Information...) to
a date later than the close of your project.

The S curve needs to be generated manually using the chart features of Excel.

If you are using P2007, the chart is available as a Visual Report directly
from P2007.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
M

Mike Glen

You could also try Project/Project Information and reset Schedule from: to
Project finish date. Bear in mind that either suggestion could make every
task critical and you will lose all flexibility.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 