How to schedule a task to start and finish with other tasks

A

avize

Hi :)

I have a task that starts with task A and finishes when task
finishes. The duration of the task is unknown a-priory and is equal t
the time lag between the start of task A and the end of task B.

How can I define such a task?

Thanks :
 
J

Jim Aksel

Select the link below, once there select FAQ and read FAQ#19 on how to create
Hammock Tasks
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 