Hi Dears,
I have a proyect and need to create Gantt to see the relations between task,
critical path , and arrange taks to do in the minimun time.
It should happend on near to 36 hours. Many of the Tasks are of couple of
hours of duration or 30 minutes, and I need to set the initial of many task .
But I can see on task the Day to do task. I can not set the Time.
For example The task "A" wil begin at Octuber 2 , at 15:00 with 2 hours of
duration,
Task " B" follow Task "A" and has 1 hour of duration.
How I can set that task will begin at 15:00 hour
I will appreciate your help
Regards
Raúl
 
G

Gérard Ducouret

Hi Raul,

Tools / Options / Views / Date format : something with 12:33 for hours and
minutes...

Hope this helps,

Gérard Ducouret
 
R

Raul

Hola (hi) Gérard,
Your help Works OK.
Thanks

Regrads
Raúl


"Gérard Ducouret" escribió:
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top