P
PaulR
Hi,
I'm new to MS Project and am using Project 2007.
I am setting up the schedule and tracking for 1 resource to do a research
report, and subsequent presentation to a group based on the results of that
report.
This resource though, is busy with other tasks and can only be allocated to
this project for maybe 1 or 2 hours per day. How can I show that in MS
Project? It seems to think the resource is 100% dedicated to the task, when
it's not the case.
Also, I have a deadline/finish date and have used that as a constraint only
on the last input task of "give presentation to group" - all tasks above that
I have not
specified end dates and just left the initial start date unchanged.
Any help would be appreciated,
thank you!
I'm new to MS Project and am using Project 2007.
I am setting up the schedule and tracking for 1 resource to do a research
report, and subsequent presentation to a group based on the results of that
report.
This resource though, is busy with other tasks and can only be allocated to
this project for maybe 1 or 2 hours per day. How can I show that in MS
Project? It seems to think the resource is 100% dedicated to the task, when
it's not the case.
Also, I have a deadline/finish date and have used that as a constraint only
on the last input task of "give presentation to group" - all tasks above that
I have not
specified end dates and just left the initial start date unchanged.
Any help would be appreciated,
thank you!