Luke in California
My depatment has a huge project file (masterProject) on every projects we
have going on. Each project in it involve resources from multiple groups and
tasks are linked many ways. The masterProject changes daily.
I'd like to maintain an detail project file (detailProject) for my group.
Here is what I like my project file to have:
1. tracks more detail (subtasks) for some tasks in masterProject my group is
working on
2. link the two projects together so any changes can be transparant to the
other project file.
3. use Project Server and Web Access for status reporting for my group
4. (this is optional) not show detailed tasks in the master schedule
Is this possible? Is using multiple projects the right approach?
Many thanks in advance!
have going on. Each project in it involve resources from multiple groups and
tasks are linked many ways. The masterProject changes daily.
I'd like to maintain an detail project file (detailProject) for my group.
Here is what I like my project file to have:
1. tracks more detail (subtasks) for some tasks in masterProject my group is
working on
2. link the two projects together so any changes can be transparant to the
other project file.
3. use Project Server and Web Access for status reporting for my group
4. (this is optional) not show detailed tasks in the master schedule
Is this possible? Is using multiple projects the right approach?