E
Extremely Frustrated Amy
I've created my project. There are several groups each group has the same
amount of subtasks. I linked the first group so that if a task has a
duration of 2 days the next task can't start till the following day of the
ending of the previous task. Fine. Now I'm on to group 2. Group 2 sub task
1 can start after Group 1 sub task 1 is complete. The duration is 2 days for
both tasks. How do I link it so Group 2 can start after Group 1 sub task 1 is
complete? Each group has a total duration of 15 days.
amount of subtasks. I linked the first group so that if a task has a
duration of 2 days the next task can't start till the following day of the
ending of the previous task. Fine. Now I'm on to group 2. Group 2 sub task
1 can start after Group 1 sub task 1 is complete. The duration is 2 days for
both tasks. How do I link it so Group 2 can start after Group 1 sub task 1 is
complete? Each group has a total duration of 15 days.