i want to know the first start date in a number of duplicate tasks

M

Martin Theobald

I have a set of tasks, repeated for a number of different countires.
I can create a summary milestone showing me the last finish date of each
repeated activity, but what I'm looking for a way to create a summary
milestone that shows when the repeated activity first starts.
 
J

Jan De Messemaeker

Hi,

If you can describe the criterion by which to group, use the grouping
feature; it makes a pseudo-summary showing start and finish of the set of
tasks grouped.
HTH
 
J

John

Martin Theobald said:
I have a set of tasks, repeated for a number of different countires.
I can create a summary milestone showing me the last finish date of each
repeated activity, but what I'm looking for a way to create a summary
milestone that shows when the repeated activity first starts.

Martin,
If you already have milestones marking the last finish then a similar
process should be used to indicate the first start. Simply set up a
milestone for each group and set the Predecessor of the milestone to be
"Start-to-Start" with the first task.

Hope this helps.
John
Project MVP
 
M

Martin Theobald

John,
thanks for your reply, I've already tried this 'SS' constraint and it
provides me with the last start date for the group of tasks, what I was
interested in was the first start date.

Cheers
Martin..
 
M

Martin Theobald

Jan,
I'll need to try the 'grouping' feature and see if it shows what I'm looking
for. Thanks
Martin..
 
J

JackD

Did you make the dependency from the start of the milestone to the start of
the task or the other way around?
The first should work. The second will give the result you describe.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top