I am updating a task progress as usual by entering an Actual Start date.
Since the task is incomplete, I specify the Remaining Duration and then
Update Project, Reschedule Incomplete Work to start after the status date.
When this is done, Project changes the Remaining Duration from the value that
I set to a lower value. This normally occurs if a task is set as Fixed
duration but in this case all my tasks are Fixed Units. If I then change the
Remaining Duration back again to the value I want, Project accepts the value
and shows the correct dates.
Why does this happen?
Since the task is incomplete, I specify the Remaining Duration and then
Update Project, Reschedule Incomplete Work to start after the status date.
When this is done, Project changes the Remaining Duration from the value that
I set to a lower value. This normally occurs if a task is set as Fixed
duration but in this case all my tasks are Fixed Units. If I then change the
Remaining Duration back again to the value I want, Project accepts the value
and shows the correct dates.
Why does this happen?