R
Ram
Hi,
Here's what I would like to do:
I have a task that runs from 26 Feb 2007 to 16 Mar 2007, 40 hours Work and
one resource assigned to it. The task type is set as Fixed Work.
Now the resource assigned to this task worked on it on 23rd Feb for 1 hour
and then did NOT work the rest of the month in February.
Now, I want to remove the residual hours for February and reschedule the
incomplete work to March but retain finish date as 16th March.
Using - Tools\Tracking\Update Project 'Reschedule uncompleted work to start
after', I set the new start date as 1 March. Now, finish date goes beyond my
desired date of 16th March. I understand that Project recalculates the
duration from the new start date and thus comes up with a new finish date.
Is there a way to configure/setup this task such that when I reschedule the
incomplete work from Feb - the total Work(40 hours) and Finish Date(Duration)
for the task remain same but resource assignment units changes ? I tried
making the task type to be Fixed Duration, but that didn't help.
Please advise.
Here's what I would like to do:
I have a task that runs from 26 Feb 2007 to 16 Mar 2007, 40 hours Work and
one resource assigned to it. The task type is set as Fixed Work.
Now the resource assigned to this task worked on it on 23rd Feb for 1 hour
and then did NOT work the rest of the month in February.
Now, I want to remove the residual hours for February and reschedule the
incomplete work to March but retain finish date as 16th March.
Using - Tools\Tracking\Update Project 'Reschedule uncompleted work to start
after', I set the new start date as 1 March. Now, finish date goes beyond my
desired date of 16th March. I understand that Project recalculates the
duration from the new start date and thus comes up with a new finish date.
Is there a way to configure/setup this task such that when I reschedule the
incomplete work from Feb - the total Work(40 hours) and Finish Date(Duration)
for the task remain same but resource assignment units changes ? I tried
making the task type to be Fixed Duration, but that didn't help.
Please advise.