J
Joe
Is there any way to have a task interrupt an existing task, then resume the
task that was in progress when the new task is complete? For example, I am
painting a room that will take 5 days. I started this task and after the 2
days of work, there is an emergency to paint another room at another
location. This task will take 2 days. I want to stop the current painting
job, go to the other paining job, finish that job (in 2 days), then come back
to my original paint job. I want to be able to have the dependency of
resuming the original paint job when the emergency paint job is complete.
Can this be done? Realizing I already started the original paint job.
task that was in progress when the new task is complete? For example, I am
painting a room that will take 5 days. I started this task and after the 2
days of work, there is an emergency to paint another room at another
location. This task will take 2 days. I want to stop the current painting
job, go to the other paining job, finish that job (in 2 days), then come back
to my original paint job. I want to be able to have the dependency of
resuming the original paint job when the emergency paint job is complete.
Can this be done? Realizing I already started the original paint job.