Alex
Hello,
Into a programme plan I am inserting project files with
different calendars.
e.g. project A has an 8 hour day set within
Tools>Options>Calendar and has an 8 hour time set within
Tools>Change Working Time. Project B has a 7.5 hour day.
The Programme Plan has an 8 hour day.
When I insert Project B into the Programme Plan the task
start and finish dates are the same, but the values in the
duration column change.
Any help on how I can prevent the change shown in the
duration column would be great.
Regards
Alex
Into a programme plan I am inserting project files with
different calendars.
e.g. project A has an 8 hour day set within
Tools>Options>Calendar and has an 8 hour time set within
Tools>Change Working Time. Project B has a 7.5 hour day.
The Programme Plan has an 8 hour day.
When I insert Project B into the Programme Plan the task
start and finish dates are the same, but the values in the
duration column change.
Any help on how I can prevent the change shown in the
duration column would be great.
Regards
Alex