G
Gil
Hi all,
In my plan I have few summary tasks, and few tasks within each one of
these summary tasks.
I do not care which task will be the first one the resources work on,
but once a resource start working on a task, I want him to finish
working on ALL the rest of the tasks within the same summary task,
BEFORE moving to a task from another summary task.
After completing all the tasks in a summary tasks, once again I don't
care which task the resource moves to.
How can I achieve that with as few links as possible (only those which
are logically needed, to keep the plan flexible)?
Thanks for any help,
Gil
In my plan I have few summary tasks, and few tasks within each one of
these summary tasks.
I do not care which task will be the first one the resources work on,
but once a resource start working on a task, I want him to finish
working on ALL the rest of the tasks within the same summary task,
BEFORE moving to a task from another summary task.
After completing all the tasks in a summary tasks, once again I don't
care which task the resource moves to.
How can I achieve that with as few links as possible (only those which
are logically needed, to keep the plan flexible)?
Thanks for any help,
Gil