I have a project that has been interrupted by our customer. This has an
unknown duration right now but I would like to reflect in the schedule what
the delay will do to our end date. I want to be able to report in our weekly
status meetings that project X is now X days behind schedule because we are
not currently working on it.
What is the best way to be able to do this? I was thinking I should insert
a task and then make all of the unfinished tasks successors to it, but then I
don't know what to do about already started tasks.
Finally how do I reflect that my resources are not working?
Thanks for any help,
unknown duration right now but I would like to reflect in the schedule what
the delay will do to our end date. I want to be able to report in our weekly
status meetings that project X is now X days behind schedule because we are
not currently working on it.
What is the best way to be able to do this? I was thinking I should insert
a task and then make all of the unfinished tasks successors to it, but then I
don't know what to do about already started tasks.
Finally how do I reflect that my resources are not working?
Thanks for any help,