Hi,
Project Pro 2003.
I have a plan with 3 named resources and 1 generic resource. The generic
resource is set to 300% availability.
I assign work to the named resources for the next few weeks and assign the
rest of the work to the generic resource.
When I level the plan Project OVER ALLOCATES the generic resource. It
assigns 16-25 days of work to the generic resource where it should only
assign 15 days/week.
The leveling I am using is week-by-week.
Can anyone explain this behavior?