A
Andrew
Hey All,
I have a couple questions that i need to see if there is a solution for or
if it is going to be a "Project" thing.
I have a task that is 5 days long, it is fixed duration and not effort
driven, i have a generic resource assigned to it and that resource has a max
of 10 people or 10000%, i assign this resource to the task at 100% or 1
person and then i change the countour to be a bell curve.
Now i recheck the duration has not changed but my work has been halved.
This happens to all of th work contours but the amout lost varies, i have
tried this using the multiple way that is allowed and inputs are changed.
any other thoughts or solutions?
The scond issue is that why am i uanble to create compound relationship ,
for example task A starts and 3 days later task B can start, but task B is
only able to finish 2 after task A. the Relations ships should be A
Start-Start + 3, A Finish-Finish +2.
Project Rejects this level of planning and dont anyone know why?
thank you
Andrew Hansen
(e-mail address removed)
I have a couple questions that i need to see if there is a solution for or
if it is going to be a "Project" thing.
I have a task that is 5 days long, it is fixed duration and not effort
driven, i have a generic resource assigned to it and that resource has a max
of 10 people or 10000%, i assign this resource to the task at 100% or 1
person and then i change the countour to be a bell curve.
Now i recheck the duration has not changed but my work has been halved.
This happens to all of th work contours but the amout lost varies, i have
tried this using the multiple way that is allowed and inputs are changed.
any other thoughts or solutions?
The scond issue is that why am i uanble to create compound relationship ,
for example task A starts and 3 days later task B can start, but task B is
only able to finish 2 after task A. the Relations ships should be A
Start-Start + 3, A Finish-Finish +2.
Project Rejects this level of planning and dont anyone know why?
thank you
Andrew Hansen
(e-mail address removed)