B
Brian
I'm new to Project but I would think there is a way to do this.
I have a task, say it takes 1 day of actual work (so, 1 person at 100%).
But, the task needs to be done by two people working together. (So,
they cannot divided up the work and each go to the seperate corners and
work).
The resources have different commitment levels. One is at 80% and one
is at 40%. How do I show that both resources are "working" on the task,
but that really it must finish at the rate of the "slowest" person.
Both of the people also have different calendars, which I have setup.
Will this cause any problems?
Does that make any sense?
I have a task, say it takes 1 day of actual work (so, 1 person at 100%).
But, the task needs to be done by two people working together. (So,
they cannot divided up the work and each go to the seperate corners and
work).
The resources have different commitment levels. One is at 80% and one
is at 40%. How do I show that both resources are "working" on the task,
but that really it must finish at the rate of the "slowest" person.
Both of the people also have different calendars, which I have setup.
Will this cause any problems?
Does that make any sense?