S
stoods
Hi,
Project is doing a great job of levelling teh resources, but I cannot figure
out how to get project to just in time various tasks. It is currently moveing
tasks with a start as soon as possible, but it I want to delay these tasks
until they are closer to the last task in a group of tasks. Ie, task 1 is
followed by task2 which is followed on by task 4 and so on. How can I level
so that the start of task 1 minimises time between task 1 and task 4?
Thanks,
Mike
Project is doing a great job of levelling teh resources, but I cannot figure
out how to get project to just in time various tasks. It is currently moveing
tasks with a start as soon as possible, but it I want to delay these tasks
until they are closer to the last task in a group of tasks. Ie, task 1 is
followed by task2 which is followed on by task 4 and so on. How can I level
so that the start of task 1 minimises time between task 1 and task 4?
Thanks,
Mike