Greg
I recently moved a project from MSP 2000 over to 2003. One of the tasks had
its start date change. Its start date is driven by a FS+lag. How could this
be? Same logic, no progress, start date different. Same project default
calendar.
its start date change. Its start date is driven by a FS+lag. How could this
be? Same logic, no progress, start date different. Same project default
calendar.