Level resources on select tasks?

T

theintern

I have 10 tasks. I'd like to know how the resources will be leveled
differently if I were to add/delete one. Is there a column with "yes/no"
which can be used to determine which tasks are included when leveled and
which aren't?

thanks
scott
 
J

Jan De Messemaeker

Hi,

Implicitly answered on your previous post. Change the resource name ofn the
"potentially deleted" tasks to a dummy name (make sure that one is never
overallocated f.i. put max units top 10000%.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 