Leveling an enterprise resource pool

C

Chris

Hello Guys,

Great help on my last question, here is a harder one for you.

We are trying to determine how MS Project levels. We need to know if you
just level a project on the client and publish to the server, if it will take
into account say you take vacation from March 21-25; you log this time into
the admin project that is set to a priority of 1000. You create a new
project with a level of 500 and assign a task to yourself for the same start
date of the 25th. If you are in the new project and try to level the
project, it will not move the task to the next week because you have
indicated you are on vacation that week in the admin project.

Do you have to create a master project to level these two projects against
each other? We have tried to create a master project, yet it still shows
the two tasks starting on the same date of March 21st. How and which is the
best way to solve this problem?

Thanks
Chris
 
M

Mike Glen

Hi Chris,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top