T
tball
I have a resource-leveling problem. I have three tasks that need 80 hours of
work performed on each. Each task starts one week after the next. Task1
uses resource 1, Task2 uses resource 1 and 2 and Task3 uses resource 1 and 3.
Task1 levels ok but Task2 uses Res2 during the first week (because Res1 is
being used on Task1) and uses only res1 for the second week. I expected the
task to use Res2 for week one but both Res1 and 2 during the second week and
the duration will. I think the duration should be 7 ½ days and it takes 10?
The same thing happens to task 3. After res1 is finished working on task 2
it should jump to task3 and work with res3 but instead res3 works for the
first week and res1 works alone for the second week
Any suggestion would be appreciated.
Thanks
tball
work performed on each. Each task starts one week after the next. Task1
uses resource 1, Task2 uses resource 1 and 2 and Task3 uses resource 1 and 3.
Task1 levels ok but Task2 uses Res2 during the first week (because Res1 is
being used on Task1) and uses only res1 for the second week. I expected the
task to use Res2 for week one but both Res1 and 2 during the second week and
the duration will. I think the duration should be 7 ½ days and it takes 10?
The same thing happens to task 3. After res1 is finished working on task 2
it should jump to task3 and work with res3 but instead res3 works for the
first week and res1 works alone for the second week
Any suggestion would be appreciated.
Thanks
tball