G
gac
I used the leveling engine to spread out the work across resources. I went
to verify the results of leveling by filtering tasks in Gantt view for a
specific resource. I know what sequence the tasks will be addressed in for
the given resource. I've intentionally NOT used predecessors to indicate
this sequence, but rather the priority field. I made sure the tasks which
should be accomplished sooner, were assigned a higher priority than others.
However, it still keeps putting some priority 200 tasks before some priority
900 tasks. Please explain the mechanism used to schedule work.
Also, if I want to manually schedule a task, how should I do so. If I
affect the leveling delay field manually, it will get overridden upon the
next leveling activity. How/when should I manually level the plan? Consider
after my initial baseline, that I'm tracking actuals and ETCs on weekly
basis, after a few weeks, all best laid plans are shot! So to report to
management how far the project has slipped, don't I need to perform another
manual levelization in order to calculate the new finish date?
to verify the results of leveling by filtering tasks in Gantt view for a
specific resource. I know what sequence the tasks will be addressed in for
the given resource. I've intentionally NOT used predecessors to indicate
this sequence, but rather the priority field. I made sure the tasks which
should be accomplished sooner, were assigned a higher priority than others.
However, it still keeps putting some priority 200 tasks before some priority
900 tasks. Please explain the mechanism used to schedule work.
Also, if I want to manually schedule a task, how should I do so. If I
affect the leveling delay field manually, it will get overridden upon the
next leveling activity. How/when should I manually level the plan? Consider
after my initial baseline, that I'm tracking actuals and ETCs on weekly
basis, after a few weeks, all best laid plans are shot! So to report to
management how far the project has slipped, don't I need to perform another
manual levelization in order to calculate the new finish date?