H
hintze1
When I level my resources, it appears working days for resources who have no
other work on a given day, are not being assigned work. I'm using a standard
schedule and it shows it as a working day but leveling is not assigning any
work to open resources. It's not consistent, it seems to be skipping
different days in the work week, especially when the schedule went into 2010.
Any ideas? Thx.
other work on a given day, are not being assigned work. I'm using a standard
schedule and it shows it as a working day but leveling is not assigning any
work to open resources. It's not consistent, it seems to be skipping
different days in the work week, especially when the schedule went into 2010.
Any ideas? Thx.