Hi,
My manager has been trying to create a project plan in Project Pro 2007.
When he levels a plan with a resource's max units at a 100% it seems to work
"fine" altought we have found some weird things going on... when we change a
resource's max units to 80% and set to "leveling can adjust individual
assignments on a task" and click on "level now" it takes about 3 minutes to
do the leveling, and pushes the project plan to end in 2049... this is weird
as our project plan is only less than 1,000 hours and we've done this before
with 2003 and didn't have these issues... has anyone seen similar patterns
or strange behavior in Project 2003? Are there any knowng bugs with
leveling?
Thanks,
Michael
My manager has been trying to create a project plan in Project Pro 2007.
When he levels a plan with a resource's max units at a 100% it seems to work
"fine" altought we have found some weird things going on... when we change a
resource's max units to 80% and set to "leveling can adjust individual
assignments on a task" and click on "level now" it takes about 3 minutes to
do the leveling, and pushes the project plan to end in 2049... this is weird
as our project plan is only less than 1,000 hours and we've done this before
with 2003 and didn't have these issues... has anyone seen similar patterns
or strange behavior in Project 2003? Are there any knowng bugs with
leveling?