K
Keith Loewen
I have a project in MS Project 2002 with 40 tasks, using 4 resources at 70%
to 80%. All tasks are fixed work. I did not link all tasks as some do not
have dependencies. I did link some as finish-to-finish. When I leveled
resources (or should I say, attempted to), Project gave a task with 23 hours
of work and a 4.1 day duration a start date of 7/15/05 and a finish date of
12/31/49. That drove all of the tasks with a finish to finish relationship
out to 2049, but the start date for those tasks then seems reasonible given
that finish date. The task in question is part of a summary task that is
linked to the other tasks as finish to finish. (The task in question is not
linked to its own summary task) I tried deleting the task with the big date
spread, but then Project did the same thing with the remaining task that is
part of the summary task with the finish to finish relationships. HELP!
to 80%. All tasks are fixed work. I did not link all tasks as some do not
have dependencies. I did link some as finish-to-finish. When I leveled
resources (or should I say, attempted to), Project gave a task with 23 hours
of work and a 4.1 day duration a start date of 7/15/05 and a finish date of
12/31/49. That drove all of the tasks with a finish to finish relationship
out to 2049, but the start date for those tasks then seems reasonible given
that finish date. The task in question is part of a summary task that is
linked to the other tasks as finish to finish. (The task in question is not
linked to its own summary task) I tried deleting the task with the big date
spread, but then Project did the same thing with the remaining task that is
part of the summary task with the finish to finish relationships. HELP!