Manis
People,
Need help with leveling.
I have a test project.
1 resource with a max unit of 80%
4 tasks
1. Pre-work - 8 hrs - fixed work - with the only available resource at 80%
(default).
2. meeting - 13 days - fixed duration - with the resource at 100%.
3. post-work - 16 hrs - fixed work - resource at 80%
4. post-work meeting - 25 days - fixed duration - resource at 100%
The above is all I have in the plan. When I try to level (day by day, entire
project on standard leveling order, leveling can adjust individual
assignment, can create split), project says it cannot level.
All I have is 1 resource and 4 tasks! Why won't it level such a simple
project? I have been able to work around. But, I need to understand why
leveling will not work for the above scenario.
I can send my MPP file. Let me know.
Thank you!
Need help with leveling.
I have a test project.
1 resource with a max unit of 80%
4 tasks
1. Pre-work - 8 hrs - fixed work - with the only available resource at 80%
(default).
2. meeting - 13 days - fixed duration - with the resource at 100%.
3. post-work - 16 hrs - fixed work - resource at 80%
4. post-work meeting - 25 days - fixed duration - resource at 100%
The above is all I have in the plan. When I try to level (day by day, entire
project on standard leveling order, leveling can adjust individual
assignment, can create split), project says it cannot level.
All I have is 1 resource and 4 tasks! Why won't it level such a simple
project? I have been able to work around. But, I need to understand why
leveling will not work for the above scenario.
I can send my MPP file. Let me know.
Thank you!