D
D. Albert
Hi all,
I'm trying to "level resources", sounds great, but doesn't work the way I
want it to be. I got a recurring task of 2hrs every day on a resource, let's
say "DA". Now I know DA got a project that had to be finished on 2007/01/31
where she needs 16 hours for. So, my mind says that I got to start not at
2007/01/30 but already at 2007/01/29 to get it ready by end of january
(because of a calender saying DA got to work for 8 hours a day). But Project
is telling that it cannot resolve the overallocation... I tried similiar
features of the properties of project, so is there anyone who can help me?
Thanks,
D. Albert
I'm trying to "level resources", sounds great, but doesn't work the way I
want it to be. I got a recurring task of 2hrs every day on a resource, let's
say "DA". Now I know DA got a project that had to be finished on 2007/01/31
where she needs 16 hours for. So, my mind says that I got to start not at
2007/01/30 but already at 2007/01/29 to get it ready by end of january
(because of a calender saying DA got to work for 8 hours a day). But Project
is telling that it cannot resolve the overallocation... I tried similiar
features of the properties of project, so is there anyone who can help me?
Thanks,
D. Albert