J
jrichardson
One of the project plans I am working on appears to
resouce level correctly (resources are leveled at 40hr/wk
and the end dates for the phases are acceptable).
However, the individual tasks within the plan have been
broken up into very small pieces (i.e. .02 hrs/week) and
spread across the entire duration of the phase (up to 3
months). Tasks with higher priorities will get split out
far enough that lower priority tasks (same resource) will
finish sooner.
This is not just 1 or 2 tasks but the majority of them.
I've leveled plans before and I've seen this issue
previously caused by predisessors/successors linked at the
phase level. I removed the dependancies between tasks and
created milestones to link them to instead - no
difference.
All tasks are fixed work, effort driven, ASAP. Work,
resources, and priorities (rangeing from 800-500) are the
only information manually entered (duration and
start/finish dates were calculated by Project). This is
not a complex plan there are less than 1000 lines and many
of those are phase levels or milestones.
Any ideas?
Thanks,
John Richardson
resouce level correctly (resources are leveled at 40hr/wk
and the end dates for the phases are acceptable).
However, the individual tasks within the plan have been
broken up into very small pieces (i.e. .02 hrs/week) and
spread across the entire duration of the phase (up to 3
months). Tasks with higher priorities will get split out
far enough that lower priority tasks (same resource) will
finish sooner.
This is not just 1 or 2 tasks but the majority of them.
I've leveled plans before and I've seen this issue
previously caused by predisessors/successors linked at the
phase level. I removed the dependancies between tasks and
created milestones to link them to instead - no
difference.
All tasks are fixed work, effort driven, ASAP. Work,
resources, and priorities (rangeing from 800-500) are the
only information manually entered (duration and
start/finish dates were calculated by Project). This is
not a complex plan there are less than 1000 lines and many
of those are phase levels or milestones.
Any ideas?
Thanks,
John Richardson