A
andrewbettany
Hi,
I am getting confused with leveling
i want to schedule a weekly meeting for 2 hours with my team.
However this then causes problems with their (our) other assignments
When I manually reduce the assignment work to 6 hours so that the total is
8hrs, the resource is still over allocated (red). (if I reduce to 0 or
reallocate that work to someone else all is fine, but I need them still to
work 6hrs - ie the remainder of the day on the task)
Even if I add back the 2 hours to the end of the task to compensate the
resource is still in red.
what can I do ?
I am wary to level the project since my step-step book tells me to be wary
of this since it can get confused and upset stuff.
Kind regards
Andrew in Sheffield (UK)
I am getting confused with leveling
i want to schedule a weekly meeting for 2 hours with my team.
However this then causes problems with their (our) other assignments
When I manually reduce the assignment work to 6 hours so that the total is
8hrs, the resource is still over allocated (red). (if I reduce to 0 or
reallocate that work to someone else all is fine, but I need them still to
work 6hrs - ie the remainder of the day on the task)
Even if I add back the 2 hours to the end of the task to compensate the
resource is still in red.
what can I do ?
I am wary to level the project since my step-step book tells me to be wary
of this since it can get confused and upset stuff.
Kind regards
Andrew in Sheffield (UK)