G
Gilgamesh
Hello,
I have a series of almost identical tasks (over 300) where the only
difference is a resource assignment and some work hours.
I was wondering if there was a way of limiting the number of these that
occur simultaneously to 3 without setting up a lot of predecessor
relationships.
I know I can add a resource to the task and resource level but this changes
the work value on the task and the work hours is something we track by so
this is not desirable. I was thinking I might be able to add a material
resource for this but haven't been able to figure out the right way.
Thank You
I have a series of almost identical tasks (over 300) where the only
difference is a resource assignment and some work hours.
I was wondering if there was a way of limiting the number of these that
occur simultaneously to 3 without setting up a lot of predecessor
relationships.
I know I can add a resource to the task and resource level but this changes
the work value on the task and the work hours is something we track by so
this is not desirable. I was thinking I might be able to add a material
resource for this but haven't been able to figure out the right way.
Thank You