Is there anyway to link resources so that they dont join into another task
until they finsish thiers? Im using the delay on the resource schedule now to
accomplish this but find it time consuming when it is a big project with many
small tasks.

I would like to be able to link resources into the linked task so project
would automatically caculate time needed. Thanks for the help.
 
J

Jim Aksel

If "Fred" is assigned to Tasks A&B and you do not want "B" to start until
Fred finishes on A, you should use resource leveling and a priority to
accomplish this.

Some people are tempted to link A&B as Finish To Start but this is using
schedule logic to solve a resource allocation issue.

Leveling is accomplished through Tools/Resource Leveling...
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top