B
Bill Swain
I have tasks that are fixed durations, lets say one week. The resources
assigned need to be different for each day. For instance the engineer will
work 8 hrs the first day, 6 the second, and 4 the third, and two on the 4th
and 5th day. The technician however will be working in reverse as he takes
over the hands on task so he would be 3 hours the first day, 4 the second, 6
the 3rd, and 8 on the 4th and 5th.
I think I understand how to set resource availability by dates in the
resource tab, but that wouldn't move with the task if things slide and
change. How do I set this type of work loading for resources to a task so
the work assignments move with the task.
Our main concern is when certain tasks slip and then coincide with other
tasks in other areas of the project where we would see a resource
overallocation. e.g. a resources tasks have suddenly stacked up due to
project changes.
I would also like to use this to get the costs out in the "analyze time
data" feature.
Thanks,
Bill
assigned need to be different for each day. For instance the engineer will
work 8 hrs the first day, 6 the second, and 4 the third, and two on the 4th
and 5th day. The technician however will be working in reverse as he takes
over the hands on task so he would be 3 hours the first day, 4 the second, 6
the 3rd, and 8 on the 4th and 5th.
I think I understand how to set resource availability by dates in the
resource tab, but that wouldn't move with the task if things slide and
change. How do I set this type of work loading for resources to a task so
the work assignments move with the task.
Our main concern is when certain tasks slip and then coincide with other
tasks in other areas of the project where we would see a resource
overallocation. e.g. a resources tasks have suddenly stacked up due to
project changes.
I would also like to use this to get the costs out in the "analyze time
data" feature.
Thanks,
Bill