A
Arjun M
Friends,
I am 3 of 10 scale in MS project.Recently i have started using MS
project a lot .
I am running into a project issue which i do not have any solution.I
need your help on this.
I have several main tasks with subtasks in them.
The subtasks have a different start and end date.And the main task has
different start and end date.Even
though the sub tasks dates are changed the main task date doesnot
change.I want the main task to have the
start date of the first task and the end date of the last subtask.
I would really appreciate your help on this.
Thanks
Arjun M
I am 3 of 10 scale in MS project.Recently i have started using MS
project a lot .
I am running into a project issue which i do not have any solution.I
need your help on this.
I have several main tasks with subtasks in them.
The subtasks have a different start and end date.And the main task has
different start and end date.Even
though the sub tasks dates are changed the main task date doesnot
change.I want the main task to have the
start date of the first task and the end date of the last subtask.
I would really appreciate your help on this.
Thanks
Arjun M