Maximum hours worked per day

V

V

Login as Admin,
i) Customize Project Web Access (Left Menu)
ii) Under Track Settings, Time Period Settings,

There is a setting that allows set max hrs per day.

It is under "Maximum number of hours that can be entered
per day for a single task (enter '0' for no limit):

Thanks,
V

-----Original Message-----
Hi,

I would need to restrict in PWA the maximum of hours
worked by a resource per day to 8 hours. MSP 2003 only
accepts to restrict the maximum of hours worked per day
per task.
 