Method to add an average cost for a resource

N

Nerimo

I have added a Standard Cost and an Overtime Cost for my resources, but also
want to add an Average Cost, but I can't find another column to add to the
Gantt that seems to be usable for this. Hoping someone may know a way.
Thx!
 
M

Mike Glen

Hi Nerimo,

Welcome to this Microsoft Project newsgroup :)

There is no Average Cost field. However, you could insert a Cost field eg
Cost1 and put a formula in it like Cost + Overtime Cost / Work.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 