Microsoft project 2003

A

atlanta5555

After building a project that has end date and start date, its shows
duration. is there a column, etc that you can add that will tell/show you
the # of days remaining
till end date. I.e. --- a count down calendar??
 
J

JulieS

Hello atlanta5555,

If you are tracking your project by entering actual duration (how
many days you've spent since the start), Project will automatically
calculate the remaining duration. Take a look at the Tracking table
for Actual and Remaining Duration fields.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 