WilliamsK said:
Finish Date vs. Actual Finish Date - Is there a way to enter a Finish Date
and not have that date change when you enter the Actual Finish Date?
Currently if I have a Finish Date of 1/10/05; but Actual Finish Date was
1/18/05, the program automatically changes the Finish Date to 01/18/05. This
drives me crazy because it is giving inaccurate date.
Thanks for the help!
Kathy
Kathy,
First of all, you shouldn't be entering Finish Dates (or Start Dates).
The main premise of Project is to calculate a schedule based on primary
input data. That primary data consists of:
1. Entering a action based description of tasks to be performed
2. Estimating a Duration for each performance task based on historical
information or educated guesses
3. Setting up linkages between tasks that establish a logic flow of the
tasks to be performed
4. Assigning Work and resources to perform the tasks
Those are the basics. From the Duration and linkages, Project will
calculate all task Start and Finish dates. On rare occasions the user
may need to directly input a task Start date if that task is independent
of any predecessors and is likely to start after the beginning of the
project. For example, a resource only becomes available to start a task
a few months after other project tasks have started.
Now, with regard to Finish and Actual Finish. The Finish field is the
original estimate (calculated by Project) of when the task will be
complete. If the task actually finishes early (or later), the original
estimate is null and void because the Actual Finish has now been
determined. If you want to track performance to the original plan, a
baseline should be set (Tools/Tracking/Save Baseline) before any work is
performed on the plan. With later versions of Project several baselines
can be set to allow tracking the effects of major schedule changes. If
you need to track earned value, a saved baseline is the data used by
Project to calculate EV parameters (e.g. BCWP, CPI, etc.).
Hopefully this gives a little clearer picture.
John
Project MVP