microsoft project

D

dc

I have three tasks in project. How can I change the weight of each task to
better reflect the actual % complete, when it does the calculation by
duration?
 
J

John

dc said:
I have three tasks in project. How can I change the weight of each task to
better reflect the actual % complete, when it does the calculation by
duration?

dc,
I'm not sure what you mean by "...change the weight...". If you want to
track progress by the amount of work completed then use % Work Complete
instead of % Complete.

John
Project MVP
 
D

dc

Thanks for the reply John.

John said:
dc,
I'm not sure what you mean by "...change the weight...". If you want to
track progress by the amount of work completed then use % Work Complete
instead of % Complete.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top